November 16, 2026

Why Is Broomfield Breaching Its Own Contract to Kill Its Long-Promised Town Square?

The City picked the lake, signed a contract promising good faith, and approved every building. Now it is citing its own requirements as reasons to kill the project. We put the City on formal notice of default in September, and filed a lawsuit when the City failed to cure the default.

A short 36 months ago, Broomfield unanimously approved every building, every parking space and the lake itself, down to the last foot of shoreline, in the Town Square meant to be the heart of the city. Now the City is citing those same buildings, parking spaces and lake as its reasons to kill the project.

Nothing about the plan has changed, and neither have the rules. The standards Council used to approve it are essentially the same today, the zoning is the same, and staff’s own memo admits the City’s 2016 Comprehensive Plan “remains the adopted plan.” The only thing that’s changed is the City’s answer.

Broomfield isn’t fighting a developer’s plan, it’s fighting its own.


Broomfield asked for this

We didn’t come to Broomfield looking for a project, Broomfield came to us.

In 2016, the City asked City Street Investors and the late Dana Crawford to do for Broomfield what they had done together at Denver Union Station: go out and listen, and find out what the people of Broomfield actually wanted for the heart of their city.

Over seven months we held dozens of meetings and focus groups with Broomfield stakeholders, including visual preference surveys and use surveys, some with more than 400 questions. We put everything into a report for the City. Residents told us:
•      Make it iconic and beautiful, a place anyone would instantly recognize as Broomfield from a single photo.
•      Make it a place to linger, not just pass through.
•      Fill it with local businesses, not chains.
•      Give seniors a way to downsize without leaving Broomfield.
•      Give Broomfield a core gathering place, something its citizens would be proud of.

Underneath was a bigger idea. For 65 years, Broomfield has been a city without a center, and this was meant to be it: the heart of Broomfield, its crown jewel, the one place that would finally pull the whole community together.

Then the City held a design competition. Four planning firms got that report and the site boundaries and nothing else: no unit counts, no square footage, no instructions. When the plans came back, the City picked the winner, not us. It chose the Civitas plan with the lake. RRA Exhibit A-1 2018 Site Graphic

At that point our consulting work was done. But the City asked City Street Investors to stay and build the project. Outpost Partners (then Milender White) joined as co-developer, and together we formed Broomfield Town Square Alliance.


The City put the vision in writing, then approved it three times

On November 12, 2019, City Council passed Ordinance 2108 approving our Redevelopment and Reimbursement Agreement. The ordinance itself called the project “a 2019 priority for City Council” and “a significant step toward making the Civic Center project a reality.” Nov 12 2019 Council Packet- 11(a)

The agreement spells out exactly what the City asked for. Exhibit D lists it: a substantially enlarged pond wrapping around the library and auditorium, an extensive plaza, about 25,000 square feet of local shops and restaurants, at least 365 homes, and a new life for the old Safeway. Exhibit A-1 is a picture of it, showing the same lake that’s in today’s plans. Exhibit E even makes the lake and the wall around it the City’s responsibility to maintain. The City signed all of that in 2019.

The agreement also says the City will “expedite the review and processing” of our applications (Section 4.5). And it says every party will act in good faith and won’t unreasonably “withhold, condition, or delay any approval, acceptance, or extension of time” (Section 36.0).

Then the City approved the project two more times. In September 2022, after residents packed the council chamber, Council voted unanimously to approve the zoning. A year later, after 16 months and eight rounds of review, Council unanimously approved the Site Development Plan, including the exact heights, density, parking and lake that City staff is now attacking.

We aren’t asking to build our project, we’re asking to build yours.


The partnership became a fight

Not long after we signed, City Manager Jennifer Hoffman came to our offices and asked us to dial the project way back, starting with eliminating the lake.

We told her the truth. The lake wasn’t ours to give away. It came out of months of community engagement, the City picked it, and it was written into the agreement Council had just approved. Dropping it meant telling residents “never mind” and renegotiating the whole deal. We said no.

From that point on, every step was a fight. The City had already done a fiscal impact study when it set up the urban renewal district. Then in 2022, with the zoning vote coming up, it commissioned a second study that concluded the project would cost the City money. The vote slipped about six months while we hired our own consultant to answer it. Residents showed up anyway, and Council approved the zoning unanimously.

The site plan took 16 months and eight rounds of revisions. Then came the construction drawings: more than two years and over $1 million in design and engineering to produce permit-ready plans for $30 million of infrastructure, including the lake, swim beach, plazas, streets, sidewalks, sewers, floodway work and trail connections. All the while, the City kept adding requests for off-site improvements and more engineering studies.

Then the goalposts moved. In November 2025, the City’s planning director told us in writing that the three-year deadline would be met by “the first building permit issued for the property.” Ten weeks later, the deputy City Manager reversed it. Our boathouse and restroom permits wouldn’t count, even though, in her own words, “the code does not explicitly limit which type of building permit qualifies.”

We asked for 18 months to work within the City’s new reading of its own code. The City’s answer, this August, was an offer to pay us $2 million to go away.
Denver Business Journal, Aug. 6, 2026.

The agreement says the City will act in good faith and will not “unreasonably withhold, condition, or delay any approval, acceptance, or extension of time . . . .” Refusing a reasonable extension on a deadline the City itself redefined breaks both of those promises. On September 22, we put the City on formal notice of default. The contract gave it 30 days to cure. It didn’t. The City is in breach of its own agreement.


Where did the three years go?

It’s a fair question; if the deadline was three years, why didn’t we have permits for the apartments and the market hall?

Because that’s not how a place like this is built. The infrastructure has to be built first. The lake, the streets, the utilities and the plaza have to exist before a single building can go up around them. That’s the $30 million of infrastructure we spent more than two years and more than a million dollars designing, because the City kept sending us down rabbit holes with changes and new scope, some of which wasn’t even a part of the project.

The buildings come after, and so does the money to design them. This project was always going to be built in phases. Phase one is the infrastructure, paid for by bonds. Those bonds also repay the millions we’ve already spent out of pocket, and that money pays for phase two: drawings for the buildings themselves, each a multimillion-dollar, multistory project the plans for which alone would cost over $1 million each. Neither we nor any lender or residential partner would spend that before the infrastructure is even permitted. The City knew this. Its own 2023 Improvement Agreement calls for the infrastructure to be built first, in the order needed to support the buildings.

It’s also exactly the order the City knew we were following. In November 2025, its planning director confirmed in writing that the first building permit would satisfy the deadline, and that “additional permits may follow at a later date for the remaining buildings.” We followed the City’s own instructions, and then the City changed them.

The truth is, we were on track. Our infrastructure permitting was underway. Permits for the boathouse and for a building housing the public restrooms and the lake’s water treatment system were also on their way, and those are real buildings by any definition. If the City hadn’t moved the goalposts, we would have met the deadline.
Even after the City’s reversal, we kept going. In March we submitted $30 million of construction plans and our building permit applications, hoping the City would see reason. When it refused to extend the deadline, we did the only responsible thing and put our pencils down. What should we have done? Kept pursuing a project the City told us it was going to revoke? The City says we delayed when we didn’t keep pursuing efforts that the City had already rejected.


Now the City is attacking its own project

On October 26, City staff asked the Land Use Review Commission to recommend revoking the site plan. The staff memo Oct. 26, 2026 LURC Staff Memo lists what the City now calls problems:
•      The lake, which the City picked, wrote into the 2019 agreement, agreed to maintain and approved in 2023. Now staff is worried about water (more on that below).
•      Building height and density along Main Street, which Council approved in the 2022 zoning and again in the 2023 site plan.
•      491 apartments, well inside the 643 Council allowed and above the 365-home minimum the City wrote into its own agreement.
•      Parking, including the shared-parking plan and variance Council approved in 2023.
•      The market hall, the reuse of the old Safeway that the City’s own agreement called for.

The City asked for, contracted for or approved every one of these, and it’s using each one as a reason to kill the project.

The same memo also admits revocation solves nothing. The agreement stays in force, and so does the zoning. Any new site plan “would need to be consistent with the approved Planned Unit Development Plan and RRA.” So revoking the plan doesn’t free the City to build something else. It just sends everyone back to the start for years of design, review and hearings, only to end up right where we are today.

Every year of redesign and re-review costs Broomfield taxpayers in staff time and consultants. It costs us, too. We’ve already spent more than $1 million on construction drawings that revocation would throw away.

Here’s what revocation means for you. The old Safeway stays empty, the field next to City Hall stays a field. The lake, the plaza, the local shops and the homes for seniors all go back to the drawing board, for years.


About that water

By the City’s own numbers, filling the lake takes about 9.2 million gallons of water, once. That’s roughly what 88 single-family homes on the Front Range use in a year. The average Denver-area home uses about 104,000 gallons a year.

After that, evaporation takes about 13.7 acre-feet a year, or 4.5 million gallons. That’s about what 43 homes use. The City’s own memo rates it at 27 tap equivalents, meaning the water allotment for about 27 houses. Broomfield used about 380 million gallons on its parks and landscaping in a single year. Keeping the lake full would take about 1 percent of that. One percent — to finally create the crown jewel Broomfield has wanted for 65 years.

And under the 2023 maintenance agreement, it’s the developer or the metro districts, not the City, that supply the top-off water and pay its roughly $1 million water license. The City’s share is the first fill: about $34,000.

Now look at the whole project. The first phase has 491 homes, nearly all of them apartments. A Denver-area apartment uses about half the water of a single-family house, 133 gallons a day versus 271. Add the lake, which is open to everyone in Broomfield, not just the people who live there. The homes and the lake together use about as much water as 285 single-family houses. That’s 491 homes and a 4.5-acre lake on the water budget of 285 houses.

By the City’s own count, 1,493 apartments have been permitted or started in Broomfield since 2023. Would Broomfield kill a 285-home subdivision over water? Of course not. So why this one?


Nobody asked Broomfield’s citizens

The City spent seven months asking residents what they wanted for the heart of their city. It ran a design competition and picked the winner. Council then approved the project unanimously, first the zoning and then the site plan.

Now City management and a majority of Council want to throw all of that out. And they haven’t gone back to residents once.

Our September 22 notice of default renewed our request that the City not seek to revoke the Site Development Plan, an action that the City is not required to do in any event, for 18 months. Council never brought that request forward for a public vote. It never heard from residents and then decided in front of them. It just plowed ahead with revocation.

Seven months of listening. Two unanimous votes. The most important place in the city, undone without asking the people it was built for. No responsible government does that.


What’s really going on?

The City says the project is taking too long, when the delay it’s complaining about is the one it caused. And its answer is revocation, which is does not have to do and which by its own staff’s account sends everything back to the starting line. If speed were really the concern, giving us an additional 18 months to meet the City’s new demand would be the fastest way forward and revocation the slowest.

And there’s no contract deadline to miss. Nothing in our agreement sets a date by which the project must be built. Section 4.3 says the developer may build all, some or none of the phases. The only clock is a line in the City’s code, which the City is choosing to enforce, despite the contract saying the City won’t unreasonably refuse to extend the time. We’re living up to our agreement, and the City isn’t.

The City also says our financing doesn’t work. What it leaves out is that nobody lends $30 million on a project whose site plan the City is threatening to revoke, and no residential partner or bond buyer will commit to one either. The City created that uncertainty in January, then blamed us for the freeze the City created.

The City says the plan no longer fits, though nothing about the plan has changed. Staff’s explanation is that a plan “may fit less well years later.” It’s been three years since unanimous votes to approve it. If three years is enough to undo one of the most important projects in Broomfield’s history, no approval in this city is safe.
And the City says it’s acting for the community, without ever asking the community.

None of that adds up, unless the goal was never a faster or better Town Square. The City has told us what it wants. In August, it offered us $2 million to end our agreement, calling the buyout “a practical business decision” that would let it “pursue a development partner capable of delivering the town center.” broomfield.org/4067, Aug. 6, 2026 update  And staff’s memo asks whether keeping the plan would limit the City’s ability to “align future development of the area with current priorities.”

Whose priorities are those, and when were they decided? And when were the people of Broomfield going to be asked?


The easy answer, the City refused

Broomfield could have settled this with one vote. An 18-month extension, which we only needed because the City moved the goalposts in January, would have cost the City nothing. The agreement it signed says the City won’t unreasonably withhold, condition or delay one.

Instead it chose revocation, which throws away nearly a decade of taxpayer-funded staff time, studies, hearings and approvals, along with more than $5 million we’ve invested. And it leaves the project in limbo for the foreseeable future.

And for what? The City says we’re free to apply for a new site plan. But we’d be submitting it to the same leaders who are working to kill the one they already approved. Nobody should believe that ends any differently.


Why winning in court isn’t enough

In October we filed suit to stop the revocation. We’ve decided to withdraw it.

Not because we think we’d lose. We believe we’d win. The contract is clear, the City’s own emails are clear, and the City never cured its default.

The problem is that if we win, we’d still lose.

A court order can stop one revocation. It can’t make a partner act like one. We’d still be tied to the same City management that has been hostile to this project for years, and a Council majority that has gone along with it. They’ve worked to derail this project again and again. They asked us to cut the lake months after we signed. They commissioned a second study to stall the zoning. They moved the goalposts on the deadline, then offered us $2 million to go away. The City has flagrantly breached the plain terms of an agreement it wrote and signed, and its leaders have spread misinformation about delay and water that the City’s own records contradict.

That’s more than a violation of the good-faith clause in our contract. It’s an ethical failure. Broomfield’s leaders didn’t just make a promise to a developer. They made it to the residents who spent seven months telling us what they wanted, and they’re breaking it without ever asking them.

How can anyone be expected to move forward with a partner like that? No reasonable partner would. And we’d be paying for the privilege: well over $100,000 in legal fees just to make the City do what it already promised, while the City squanders taxpayer money fighting a project its own residents asked for. A partner doesn’t make the other partner go to court to argue over whether a building permit is a building permit.

Here’s the good news. Our agreement doesn’t expire with this City Council. It runs for another 18 years, and the City’s own staff acknowledges it stays in force whether or not the site development plan is revoked. Elected officials come and go, and Broomfield’s citizens get to hold theirs accountable on election day.

We look forward to making the citizen-led vision for Broomfield’s Town Square a reality. We’re confident that new leadership, free of the acrimony that has poisoned this relationship, will faithfully honor the terms of our agreement and, just as important, the promises made to the people of Broomfield.

Until then, the ball isn’t in our court. It’s in Broomfield’s. We remain fully committed and ready to build this extraordinary place. We just need the partner we started with.

Broomfield, we’re here when you’re ready.


What Broomfield’s citizens can do

On December 8, City Council will decide whether to revoke the site plan. Show up, or write your council member, and ask for one thing: put our extension request to a public vote before revoking anything. Then ask the question no one at the City has answered: if not this project, then what, and how many more years will it take?

Every vote that night is on the record. A year from now, Broomfield elects new leadership. Remember it.

Broomfield asked for this. Broomfield should get to decide.

City Street Investors and Outpost Partners are the developers of Broomfield Town Square, through Broomfield Town Square Alliance.

Post from James Marsh-Holschen, Broomfield mayoral candidate and former Ward 1 Council Member – October 28, 2026

What might a day in the life of our Town Square be like?